pull down to refresh

USD/BTC =$95,344 Block 895,203 TL:DR
The U.S. Army Corps of Engineers, Galveston District has awarded a $403,944,000 contract to Kiewit U.S. Contractors to construct additional portions of the Port Arthur Project, a component of the Sabine Pass to Galveston Bay (S2G) Coastal Storm Risk Management Project.
The Port Arthur Project provides critical improvements to increase the level of flood protection, or risk reduction, provided by the existing hurricane protection system in Port Arthur.
Under the awarded Contract PAV04, construction will include the replacement of 9,525 feet of floodwall, 2,300 feet of levee raises, four levee-floodwall tie-ins, and fronting protection at three pump stations.
These upgrades are intended to enhance the reliability and performance of the existing hurricane protection system.
Construction of this work is expected to begin in Summer 2026 and take approximately three and a half years to complete.
According to USACE, this important initiative will protect the people and businesses of Port Arthur when completed and contribute to the long-term security of the entire Gulf Coast region.

My Thoughts 💭

Flood protection is very very expensive. Almost 5,000 BTC to protect Port Arthur from flooding. I am assuming this will protect the city from a 500 year storm. But 1,000 year flood this city might be toast. But that is the cost being next to the water.
Curious -- do you work in construction? I used to work for an ConTech company that made hardware + software for the industry...although I don't work there anymore, it's interesting to see some old names like Kiewit on there (I worked closely with the InEight team to launch an integration with them).
reply
Indeed I do
reply